Project Description

About the PP13 Power Plant project

This 1,800MW plant is being constructed in Dhurma, about 140 kilometres west of Riyadh, next to the existing PP12 plant. Its purpose is to increase the power capacity in the region and is constructed in several major packages. The project is estimated for completion in 2021.

Challenges & solutions

CDI Experts were retained by Worley and Saudi Electricity Company to provide claims advisory, contractual, delay and quantum analyses of Contractor claims across several packages of work.

Our analyses helped to show that Contractors delay, disruption and cost claims were almost entirely unfounded.

We continue to provide support to the project management team as the project enters the final commissioning phase.

Project Location Riyadh, Saudi Arabia
Client Name Saudi Electricity Company
Project Name PP13 1800MW Combined Cycle Power Plant
Project Value $2,000,000,000
Project Start Date May 2015
Project End Date Ongoing
Sector Energy